| |
It
has been almost three months since the last Dispatch, about
twice as long an interval than usual. What, dear reader, might
have caused such a delay? A headlong, all-out work blitz to
have the place ready for sesshin by September 28? Yes.
And ready it was.And now the first sesshin at Chapin Mill is
history.
After months of Lou's pleading with local sub-contractors to
come and finish off the work required to get a Certificate of
Occupancy, they finally swooped in with their teams in the nick
of time. Four electricians spent days installing lighting in
the temporary zendo, the hallways, the entryway steps outdoors,
and the dining room. Many of their hours went toward the code-required
emergency lighting and the industrial-strength appliances in
our big kitchen. Our very talented plumber also spent much of
his time in the kitchen getting us up to code. The bathrooms
were tiled. Bronze handrails were affixed to the entryway steps.
Another sub-contractor had a team outdoors with backhoes and
front-loaders, doing final grading for the building and the
area behind it where Phase 2 will eventually go. (They also
put in a septic system for the older buildings, on the other
side of the creek, with a new pumping station, two tanks, and
drainage field.) A slew of newly-required fire doors were installed.
Carpeting was laid throughout the dorm rooms and corridors.
But the real tributes for the two months leading up to sesshin
must go to the ZC staff and other Sangha volunteers. Besides
the indefatigable foreman of the project, Lou, always at the
center of things, Alan Temple spent more time than ever on-site,
supervising maha-landscaping work and the installation of drainage
and septic systems. He also oversaw Eric Scheider's and Holger
Steinsträter's two weeks of continuous labor in laying the bluestone
for the terrace to the main entrance. Mike Hurd and Britta Brückner
(who, like Holger, is a key member of our Berlin affiliate group)
mudded and sanded their way through the basement, helped as
usual by John Pulleyn and Lou. This was the "final assault"
in our 18-month drywall campaign. Tom St. Pierre continued to
employ his woodworking talents to put in doors, baseboards and
stairway handrails, joined occasionally by Mike Chrest and Angel
Martinez. During the Ralph Chapin Memorial Work Week the oak
flooring in the dining room got four coats of protective sealer,
a meticulous, time-sensitive operation that took a team of four
the better part of two days. And then there was the prodigious
job of cleaning up two years of dust and debris.
The climax to all this effort came with the visit of the building
inspector just five days before the sesshin. On his previous
visit he had given us reason to be confident that, despite additional,
unexpected requirements he had specified, he would finally grant
us the Certificate of Occupancy we needed to hold sesshin. And
lo! two days later we had the C of O in hand!
And then we shifted into high gear. In the remaining three
days before sesshin the staff, mostly, had to move everything
we needed from Arnold Park: mats and cushions; dividers; kitchen
equipment, plates, bowls, utensils, food, and other supplies;
folding chairs for the dining room, chair zendo, and dorm rooms;
bathroom supplies, housekeeping supplies and equipment; and
mattresses. After thrashing out a decision to hang wood mini-blinds
in the twelve zendo windows, Helen Fuller did the follow-through,
as she had done for the carpeting and tiling and some interior
elements. That Friday Amala and I spent most of the afternoon
in the zendo, working out an experimental seating configuration
around the central altar. Our Arnold Park facility was all but
deserted now, and sesshin participants from Germany, California,
and other distant points were beginning to arrive at Chapin
Mill.
On the eve of sesshin Murphy's Law kicked in. A tractor-trailer
loaded with mulch (for work in on the gardens during sesshin)
rolled into Chapin Mill through a steady rain, slid on the muddy
road, and nearly tipped over into the pond; its many wheels
on one side were hanging in the air. With the help of local
support, the spill was cleaned up and disaster averted-but it
was not something that had been on our work lists.
The next day found all hands on deck, bent to the myriad tasks
required to get any sesshin launched, but now without our trusty
Arnold Park check lists. We were sailors scurrying over a ship
soon to leave on its maiden voyage: heaving, testing, repairing,
arranging, improvising. And cleaning, cleaning, cleaning.
Sesshin started on time that night. Just a year or so later
than many of us had hoped.
Sesshin, Al Fin
For the first couple days of sesshin the four monitors and
I (four of us having worked for years on the Building Committee)
were airborne. Amala remarked that when she walked around the
bend in the road before the opening ceremony the first night
and saw the building lit up and full of people, it was like
coming down the stairs on Christmas morning as a girl and seeing
the tree aglow. But there was little time in which to savor
our accomplishment. The monitors and I spent most of every break
period that week meeting together, problem-solving and working
out new procedures and policies for this experimental sesshin
that involved the three older buildings as well as the new one.
Lou was so busy that he couldn't find time to take a nap until
after dinner on the sixth day. But our energies were continually
renewed by the country air, the pond, and the sounds of the
geese, the waterfall, and the silence.
Participant's Responses
After sesshin I asked participants to write down three things
they liked about sesshin at this new facility. Here are direct
statements that reflect the most frequently mentioned features:
a.. "beautiful country setting"
b.. "the sounds of nature, the train whistle-and the quiet"
c.. "the spaciousness, inside and out"
d.. "the Buddha altar in the center of the zendo"
e.. "the chair zendo is a breath of fresh air-literally"
f.. "the bright, efficient, roomy kitchen"
g.. "chairs at the dining room tables"
h.. "the beauty of the lighting, the wood trim, and the painting"
i.. "going for a walk at night with hundreds of crickets shouting
encouragement"
Participants also brought forth some constructive criticism,
most of it raised earlier by the monitors in our frequent meetings:
there was just too much empty floor space in one half of the
zendo (which, remember, was designed as an exercise room suitable
for 60-some people); too much kitchen/dining room noise heard
in the chair zendo, and in the zendo itself; and lesser problems
due to the not-quite-finished state of the place. These and
other problems are being addressed.
Speaking personally, throughout the week of sesshin, in all
my comings and goings, indoors and out, I felt as though bathed
constantly in gratitude toward the many, many people (most of
whom were not even in this sesshin) who brought us to this epochal
event: donors large and small, volunteers beyond count, our
architects, even our hired tradesmen-and yes, the Building Inspector.
What more could anyone ask for?
Well, all right, there is Phase 2 to take on some day. But
never mind that for now.
Click here
for more photos of the first Chapin Mill sesshin. |