|
These
informal reports, filed every couple weeks by Sensei (and e-mailed
to interested members), are meant to provide snapshots of what's
happening at Chapin Mill, plus the who, how, when, and where
of it.
Those of you hoping to attend the first sesshin at Chapin Mill
in July may now accept delivery of a consolation prize: a Special
Teaching on dukkha, or dissatisfaction (in the face of another
delay); kshanti, or forbearance (ditto); and even sunyata, or
emptiness (of goals, attainments, whatever). That's right, Chapin
Mill will not be ready for the July sesshin.
To get a certificate of occupancy, all of the safety devices
required by local and state codes must be in place. During his
last visit the Stafford building inspector revisited a number
of issues that we thought had been resolved long ago, such as
certain fire doors and stove fire extinguisher systems. Through
our architect John Bero we are presently working to resolve
these questions, but we also just learned that our building
inspector will be out of town from June 23rd to July 8th, meaning
we will not be able to get our occupancy permit in time for
the July sesshin.
Though we recently set the July sesshin as a goal that would
help us mobilize our efforts, many of us are now breathing a
sigh of relief. It would have been
a race to the wire to get the kitchen equipped, more rooms and
bathrooms painted, plumbing fixtures installed, the zendo floor
finished, and additional electrical work in the kitchen done.
There was also the issue of code-mandated handrails on the front
stairway and in other areas, the bluestone patio area in front
of the main entrance front door that must be finished, etc.,
etc., etc.
But neither have we been twiddling our thumbs out there. (Their
tips lightly touching for some hours each day, in the gorgeous
temporary zendo, yes, but twiddling, no.)
The
blue-gray slate in the foyer and main entranceway has been installed.
The temporary zendo/exercise room is almost ready for painting,
and floor finishing there will begin shortly. A lot more woodwork
has been installed in the dormitory wing and elsewhere. The
porch floor, which we had to stop working on when the cold blew
in last fall, is now nearly finished. Still more drywall work,
as well as mudding and painting, has been done. A great deal
of the woodwork in the upstairs dormitory hall was finished
recently.
All of the kitchen cabinets are installed, but we are waiting
for the stainless-steel tops. A special layer of vapor-proof
paint was added to the kitchen dishwashing area ceiling, in
anticipation of the 180-degree steam that will billow from the
dishwasher after each tray of dishes comes out. The cold room
cooling unit has been installed.
Meanwhile,
the most dramatic visual improvement is at hand: the painting
of the stucco-coated lower half of the building. So far it has
remained its original gray, and just begging for color. Help
came from south of the border in the person of Gerardo Gally,
Sensei, newly-authorized teacher and longtime leader of Casa
Zen. Gerardo-sensei is not only an architect (and owner of a
publishing company), but something of a color expert. He generously
agreed to spend a few days at Chapin Mill recently to come up
with a color scheme for the stucco. Some experimenting remains
to be done on that, but of this much we are sure: a major color
will be a dark, "Chinese" red. Stay tuned!
Thanks to Lou Kubicka for doing the heavy lifting on this
report.
|